Joy Henry

Florida’s Department of Transportation says an engineer left a voicemail two days before a catastrophic bridge failure to say some cracking had been found at one of the concrete span.

However, the agency says the voicemail left on a landline wasn’t heard by a state DOT employee until Friday because the employee was out of the office on an assignment.

In a transcript of the voicemail released Friday night, Denney Pate with FIGG Bridge Group says the cracking would need repairs “but from a safety perspective we don’t see that there’s any issue there so we’re not concerned about it from that perspective.

“Hey Tom, this is Denney Pate with FIGG bridge engineers. Calling to, uh, share with you some information about the FIU pedestrian bridge and some cracking that’s been observed on the north end of the span, the pylon end of that span we moved this weekend,” Pate said, according to a transcript released by FDOT.

“Um, so, uh, we’ve taken a look at it and, uh, obviously some repairs or whatever will have to be done but from a safety perspective we don’t see that there’s any issue there so we’re not concerned about it from that perspective although obviously the cracking is not good and something’s going to have to be, ya know, done to repair that. At any rate, I wanted to chat with you about that because I suspect at some point that’s gonna get to your desk. So, uh, at any rate, call me back when you can. Thank you. Bye.”

The pedestrian bridge at Florida International university collapsed Thursday, killing at least six people. Authorities are slowly removing the debris, looking for more victims.

The National Transportation Safety Board is investigating the cause of the collapse.